On December 1st, 2014, MICOMISENG city in Equatorial Guinea across the water marked by my company first
phase of the pipeline maintenance works completed smoothly.
Nine damages caused during July 2014, the French engineering company named Sofiain MICOMISENG city road
construction on the water supply pipeline, a paralysis of the pipe network, sewage plants and waterworks cease operations.
By the parties to mediate negotiations, the decision by the company admission maintenance, engineering and truly settled.
After receiving this notice, the company quickly organized the project budget andpreparations. November 1st, 2014
Mbini water project construction management department dispatched officers went to the engineering field, November 2nd
official for maintenance, repairs totaling nine damaged pipes, install five water point . Which repairs damaged two pipelines
for water pipes and sewers network maintenance, laying a total of 210 meters of ductile iron pipe DN250, De315 double
wall corrugated pipe 52 meters; The remaining seven for distribution network maintenance,otaling 265 meters pipe laying
De110PE, De63PE pipe 91 meters, De25PE pipeline 131 meters. To ensure the project was successfully completed in the
correct guidance and leadership of the companys strong support, the project manager scientific organization, the proper
deployment, overtime, to overcome the pipeline breakage scattered pipes located under the ground to troubleshoot problems
and difficulties, the successful and efficient the completion of the pipeline maintenance tasks.
After a month of unremitting efforts, MICOMISENGcity smoothly across the board through the water. The successful
completion of the pipeline maintenance task to solve the MICOMISENG city tension of the water supply difficulties and
got the local government and CGCOC Chinese Company’s fully recognition, and more to enhance our company in Equatorial
Guinea market influents, as Equatorial Guinea to further develop the market and laid solid foundation.